A

Annual Procurement Plan (APP)

All procurement shall be within the approved budget of the Procuring Entity and should be meticulously and judiciously planned by the Procuring Entity. Consistent with government fiscal discipline measures, only those considered crucial to the efficient discharge of governmental functions shall be included in the Annual Procurement Plan (APP).

For purposes of this IRR, a procurement project shall be considered crucial to the efficient discharge of governmental functions if it is required for the day-to-day operations or is in pursuit of the principal mandate of the Procuring Entity concerned.

The APP shall include provisions for foreseeable emergencies based on historical records. In the case of Infrastructure Projects, the APP shall consider the appropriate timing/phasing of related project activities, such as, engineering design and acquisition of right-of-way site or location, to reduce/lower project costs.

No procurement shall be undertaken unless it is in accordance with the approved APP, including approved changes thereto. The APP must be consistent with the duly approved yearly budget of the Procuring Entity and shall bear the approval of the HoPE or second-ranking official designated by the HoPE to act on his behalf

Upon issuance of the budget call in the case of NGAs, SUCs, Constitutional Commissions or Offices, or similar document for GOCCs, GFIs and LGUs, the Procuring Entity shall prepare its indicative APP for the succeeding calendar year to support its proposed budget taking into consideration the budget framework for that year in order to reflect its priorities and objectives.

Changes to the individual PPMPs and the consolidated APP may be undertaken every six (6) months or as often as may be required by the HoPE. The respective end-user
or implementing units of the Procuring Entity shall be responsible for the changes to the PPMPs, while the BAC Secretariat shall be responsible for the consolidation of these PPMPs into an APP, which shall be subject to the approval of the HoPE.

Changes in the APP, if any, for the budget year shall be submitted to the GPPB in July of the current budget year, and in January of the following budget year.


Approved Budget for the Contract (ABC)

Refers to the budget for the contract duly approved by the HoPE, as provided for in the General Appropriations Act (GAA), continuing, and automatic appropriations, in the case of national government agencies (NGAs); the corporate budget for the contract approved by the governing board, pursuant to Executive Order (E.O). No. 518, s. 1979, in the case of GOCCs and GFIs, and R.A. 8292 in the case of SUCs; the budget approved by the Sanggunian through an appropriations ordinance in the case of LGUs. For multi-year contracts, for which a Multi Year Obligational Authority (MYOA) or an equivalent document is required, the ABC shall be that incorporated in the project cost reflected in the MYOA or equivalent document. 

For Foreign-funded Procurement, the ABC refers to the cost estimate prepared by the Procuring Entity and approved by the foreign government/foreign or international financing institution as specified in the Treaty or International or Executive Agreement.