Negotiated Procurement- Take Over Contracts

Negotiated Procurement- Take Over Contracts

by Harvy Calabio -
Number of replies: 1

Can the Procuring Entity may still conduct NP- Take Over Contracts this year if the Public Bidding was conducted and awarded last year?

In reply to Harvy Calabio

Re: Negotiated Procurement- Take Over Contracts

by Jessie Salvador -

Yes, if the previous contract was rescinded this year.

If the rescission happened last year, you may need to check if the funding may stll be used this year.