Post-qualification of completed contract

Re: Post-qualification of completed contract

by Jessie Salvador -
Number of replies: 0

No. That will be going beyond the rules.

The post-qualification shall verify, validate and ascertain the veracity, authenticity and validity of all the other statements made and documents submitted by the bidder with the Lowest Calculated Bid/ Highest Rated Bid, using non-discretionary criteria, as stated in the Bidding Documents. 

The TWG, or principally the BAC for that matter, shall employ only non-discretionary pass/fail criterion based on the submissions. To use another evaluation system or criterion will be a violation of the rules.