Bids and Award Committee

Re: Bids and Award Committee

by Judex Donnel Llamoso -
Number of replies: 0
Pursuant to Section 12 of the RIRR of R.A. 9184, the BAC has the power and function to "create a TWG from a pool of technical, financial, and/or legal experts to assist in the procurement process, particularly in the eligibility screening, evaluation of bids, and post qualification." If the BAC deemed it unnecessary to create a TWG then they may not do so.

The BAC may accept or reject the findings of the TWG to support the evaluation or post disqualification of a bidder.

There are no standard forms for the post-qualification or evaluation reports.